Berkman Dam and Hydroelectric Power Plant
Project’s Overview
The Berkman Dam and Hydroelectric Power Plant, with an installed capacity of 39 MW, is located on the mainstream of the Ceyhan River in Osmaniye Province, southern Türkiye. Designed to make use of the river’s high flows, this low-head plant is the second of the two projects developed as part of the Ceyhan River cascade. The cascade has a combined installed capacity of 64 MW, and both projects were delivered under a build–operate–transfer (BOT) model with a 49-year concession period.
Özaltın and Nurol co-founded Enova Energy Company, and each holds 50% of its shares. Enova Energy implemented the Berkman project and currently owns and operates the plant.
The dam spans the Ceyhan River valley and has a crest length of 345 m and a hydraulic height of 16.5 m.
The powerhouse features three pit-type, horizontal-shaft Kaplan turbines, each coupled to a synchronous generator rated at 13 MW.
Work on the project began in 2007, and the plant entered commercial operation in late 2010.
The Berkman plant generates an average of 160 million kWh of renewable electricity annually. At this level of generation, Berkman is expected to reduce greenhouse gas emissions by approximately 85,600 tonnes of CO₂ per year.